Q1. | If 40 men can build a wall 300 m long in 12 days working 6; hours a day, how long will 30 men take to build a similar wall 200 m long working 8 hours a day ? |
| 1) | 4½ days | 2) | 10½ days |
| 3) | 8 days | 4) | 11 days |
| 5) | None of these | ||
Answer : 8 days
Explanation :
Explanation :
Sol. M1D1W2T1 = M2D2W1T2
or D2 = (40 x 12 x 200 x 6)/ (30 x 300 x 8 ) = 8 days
🔒 Click "View Answer" to reveal correct option
View Answer
Q2. | Three men or eight boys can do a piece of work in 17 days. How many days will two men and six boys together take to finish the same work ? |
| 1) | 9 days | 2) | 11 days |
| 3) | 14 days | 4) | 12 days |
| 5) | None of these | ||
Answer : 12 days
Explanation :
Explanation :
3 men = 8 boys
2 men =(8x2)/3 = 16/3 boys.
(2 men + 6 boys) =[(16/3 )+6] boys
= (34/3) boys
Given, 8 boys can complete the work in 17 days
(34/3 boys can complete the work in x days
34/3 : 8 = 17 : x
x =(17x8x3)/34 = 12 days
🔒 Click "View Answer" to reveal correct option
View Answer
Q3. |
|
| 1) | 5-3/10 days | 2) | 6-7/10 days |
| 3) | 6-3/10 days | 4) | 7-3/10 days |
| 5) | None of these | ||
Answer : 6-3/10 days
Explanation : A,B and C altogether work for 3 days = 3 (1/12+1/18+1/24) = 13/24 parts
Explanation : A,B and C altogether work for 3 days = 3 (1/12+1/18+1/24) = 13/24 parts
So, remaining (1-13/24) = 11/24 parts
B and C can do in 1 day (1/12+1/18) = 5/36 parts
Now, B & C can do this in (11/24 )/(5/36) = 33/10 days = 3-3/10 days
So, overall time taken to complete this workpiece = 6-3/10 days
🔒 Click "View Answer" to reveal correct option
View Answer
Q4. | A is 25% more efficient than B and 50% more efficient than C. A and B together can complete a work in 20 days. How many days the same work can be completed by B and C if both work in alternate days and B starts the work first ? |
| 1) | 48 days | 2) | 49 days |
| 3) | 50 days | 4) | 51 days |
| 5) | None of these | ||
Answer : 49 days
🔒 Click "View Answer" to reveal correct option
View Answer
Q5. |
|
| 1) | 8 days | 2) | 10 days |
| 3) | 12 days | 4) | 14 days |
| 5) | None of these | ||
Answer : 14 days
Explanation : Let, Bikas takes x days to finish the work . So, Alok would take (x +8) days to finish the same work.
Explanation : Let, Bikas takes x days to finish the work . So, Alok would take (x +8) days to finish the same work.
Given, Alok finishes 75% and Bikas finishes 25% work respectively.
So, (x+8)3/4 = (x/4)+9
or (3x+24)/4 = (x+36)/4
or 2x = 12
or x = 6
Therefore, Alok would finishes the work (6+8) = 14 days alone.
🔒 Click "View Answer" to reveal correct option
View Answer
Q6. | A fort has provisions for 250 soldiers for 35 days. After 5 days a reinforcements of 25 soldiers were arrived. Again after 10 days, 25 soldiers left the fort. How long will the remaining provisions lasting ? |
| 1) | 12 | 2) | 16 |
| 3) | 18 | 4) | 19 |
| 5) | None of these | ||
Answer : 19
Explanation :
Explanation :
Short- Cut Methods:
ND (No. of days) = N1D1 + N2D2 = total amount of food after 5 days.
or ( 250 X 30) = ( 250 + 25) X 10 + 250 X x
or x = 19 days .
🔒 Click "View Answer" to reveal correct option
View Answer
Q7. | Seven men and four boys can complete a work in 6 days. A man completes the double work than a boy. In how many days will 5 men and 4 boys complete the work ? |
| 1) | 4 | 2) | 5 |
| 3) | 6 | 4) | 8 |
| 5) | None of these | ||
Answer : None of these
🔒 Click "View Answer" to reveal correct option
View Answer
Q8. |
|
| 1) | 9 days | 2) | 11 days |
| 3) | 14 days | 4) | 12 days |
| 5) | None of these | ||
Answer : 12 days
Explanation :
Explanation :
3 men = 8 boys
2 m = (8/3)x2 = 16/3 boys.
(2 men + 6 boys) = (16/2)+6 boys = 34/3boys
8 boys can complete the work in 17 days
or 34/3boys boys can complete the work in x days
or (34/3) : 8 = 17 : x
or x =(17x8x3)/34 = 12 days
🔒 Click "View Answer" to reveal correct option
View Answer
Q9. | 10 man can finish a piece of work in 15 days. 8 women can finish the same work in 25 days. Only 10 women started working and in a few days completed a certain amount of work. After that 3 men joined them. The remaining work was completed by 10 women and 3 men together in 5 days . After how many did 3 men join with 10 women ? |
| 1) | 11 | 2) | 13 |
| 3) | 15 | 4) | 10 |
| 5) | None of these | ||
Answer : 13
🔒 Click "View Answer" to reveal correct option
View Answer
Q10. | 16 men can complete a piece of work in 8 days. 20 women take 16 days to complete the same piece of work. 12 men and 10 women work together for 6 days. How many more days would 10 women alone require to complete the remaining piece of work ? |
| 1) | 6 days | 2) | 8 days |
| 3) | 10 days | 4) | 12 days |
| 5) | None of these | ||
Answer : 8 days
Explanation : Given,16 men can complete a piece of work in 8 days while 20 women take 16 days to complete the same piece of work.
Explanation : Given,16 men can complete a piece of work in 8 days while 20 women take 16 days to complete the same piece of work.
The ratio of the capacity of doing work i.e. men to women = (20 x 16 ) : (16 x 8) = 5:2
So, 1 man = 2.5 women
Now, 12m + 10w = (12 x 2.5) = 40w
Given, 20 women take 16 days to complete the same piece of work.
Given, 20 women take 16 days to complete the same piece of work.
1 woman can do it in = 16 x 20 = 320 days i.e. 1/320 parts in 1 day.
40 women can do in 6 days = (1/320) x 40 x 6 = 6/8 = 3/4 parts
Therefore, remaining 1-3/4=1/4 part of the work done by only 10 women in =
Applying Chain Rule:
M1 x D1 x W2 = M2 x D2 x W1
or 20w x16 x 1/4 = 10w x D2 x 1
or D2 = 8 days
🔒 Click "View Answer" to reveal correct option
View Answer